Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
125W525 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 81/56 विशेष मरम्मत के अन्तर्गत/2023-24 दिनांक 23.12.2023
TS Amount (lakhs) : 4.48 Lacs
Financial Detail
Sanction Cost : 4.48 Lacs
Resanction Cost : 4.48 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 4.48 Lacs
Demand : 4.48 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
4 months 3 weeks ago
23 Dec 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-May-2024
Physical Peramenters