Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
125W529 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 182068 ई-पत्रावली संख्या 48456 दिनांक 15.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
103.60
Resanction Cost :
103.60
Tentative Cost :
103.60
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 103.60
Demand : 103.60
Allotment : 40.00
Exp in CFY : 39.26
Total Up to Date Exp : 39.26
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 60 %
Sanction on :
6 months 2 days ago
15 Jan 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 09-Feb-2024
Physical Peramenters