Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.825 | 1.825 | 1.825 | 0 |
125W530 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 192480/2024 ई-पत्रावली संख्या-38302 दिनांक 21.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 97.32 Lacs
Resanction Cost : 97.32 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 97.32 Lacs
Demand : 97.22 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
2 months 4 weeks ago
21 Feb 2024
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निर्माण कार्य प्रगति पर। -- as on 09-Mar-2024
Physical Peramenters