Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24 | 24 | 24.000 | 0 | 24.000 | 0.000 |
125W531 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 256/।।।(3)ध्2024-01(सी0आर0आई0एफ0) दिनांक 29.02.2024 द्वारा प्रशासकीय स्वीकृति प्राप्त। शा0सं0 322/।।।(3)/2024-01(सी0आर0आई0एफ0) दिनांक 16.03.2024 द्वारा वित्तीय स्वीकृति प्राप्त।
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2600.00
Resanction Cost :
2568.57
Tentative Cost :
2568.57
Exp. Upto Last Fy : 199.57
For CFY 2024-2025
Remaining : 2,369.00
Demand : 1,500.00
Allotment : 300.00
Exp in CFY : 246.32
Total Up to Date Exp : 445.90
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 25 %
Sanction on :
4 months 2 weeks ago
29 Feb 2024
Tentative Completion date:
5 months 2 days from now
20 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
25 प्रतिशत तक कार्य पूर्ण कर लिया गया है। शेष कार्य प्रगति पर है। -- as on 11-Jul-2024
Physical Peramenters