Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.45 | 4.45 | 0.000 | 4.45 | 4.450 | 0.000 |
125W586 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 191ध्14याता0(क)-उ0ध्2023 दिनांक 09.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
66.75
Resanction Cost :
66.75
Tentative Cost :
66.75
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 66.75
Demand : 66.75
Allotment : 50.00
Exp in CFY : 48.99
Total Up to Date Exp : 48.99
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 90 %
Sanction on :
5 months 1 week ago
09 Feb 2024
Tentative Completion date:
1 year 3 months from now
31 Oct 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 26-Jun-2024
Physical Peramenters