Work Profile

125W586 :

No Pic Avilable Time series Gantt
पैठाणी बडेथ नौडी मोटर मार्ग (प्रमुख जिला मार्ग) ।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0 191ध्14याता0(क)-उ0ध्2023 दिनांक 09.02.2024

TS Amount (lakhs) : 0 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

66.75

Resanction Cost :

66.75

Tentative Cost :

66.75

Exp. Upto Last Fy : 0.00

For CFY 2024-2025

Remaining : 66.75

Demand : 66.75

Allotment : 50.00

Exp in CFY : 48.99

Total Up to Date Exp : 48.99

Work completed

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 90 %

Sanction on :
5 months 1 week ago
09 Feb 2024


Tentative Completion date:
1 year 3 months from now
31 Oct 2025


Actual Completion Date:
Not Yet Reported


Rating : 719

Remark

Bottelneck: no issue


कार्य पूर्ण। दायित्व अवशेष। -- as on 26-Jun-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4.45 4.45 0.000 4.45 4.450 0.000
Currently only Bank Gaurantee information is avilable