Work Profile Report [125W588]

साकरसैण बरसीला बगड मोटर मार्ग। (ग्रामीण मार्ग)।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 संख्या 388/14याता(क)-उ0/2023 दिनांक 15.03.2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

16.05

Resanction Cost :

16.05

Tentative Cost :

16.05

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

16.05

Demand :

16.05

Allotment :

16.00

Exp in CFY :

15.99

Total Up to Date Exp :

15.99

Work completed

Sanction on : 8 months 1 week ago

15 Mar 2024

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

90 %

Tentative Completion date on : 5 months 3 weeks ago

31 May 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement

Remark

view all

कार्य पूर्ण। दायित्व अवशेष। -- as on 26-Jun-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: