Work Profile

125W592 :

No Pic Avilable Time series Gantt
निसणी बुधणी मोटर मार्ग। (ग्रामीण मार्ग)।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0 संख्या 388/14याता(क)-उ0/2023 दिनांक 15.03.2024

TS Amount (lakhs) : 0 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

73.95

Resanction Cost :

73.95

Tentative Cost :

73.95

Exp. Upto Last Fy : 0.00

For CFY 2024-2025

Remaining : 73.95

Demand : 73.95

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 0.00

Construction Started

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 10 %

Sanction on :
4 months 2 days ago
15 Mar 2024


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 60

Remark

Bottelneck: no issue


कार्य प्रगति पर। -- as on 26-Jun-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4.6 4.6 4.6 0