Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 8.000 | 8.000 |
125W595 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 257ध्14प्रा0याता0(क)ध्2023 दिनांक 20.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
143.23
Resanction Cost :
143.23
Tentative Cost :
143.23
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 143.23
Demand : 143.43
Allotment : 143.23
Exp in CFY : 143.23
Total Up to Date Exp : 143.23
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
4 months 3 weeks ago
20 Feb 2024
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 21-May-2024
Physical Peramenters