Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
125W72 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5377/।।।(2)/13-13(मु0मं0घो0)/2012, दि0 14 जनवरी 2013।
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 75.48 Lacs
Resanction Cost : 75.48 Lacs
Exp. Upto Last Fy : 60.45 Lacs
For CFY 2024-2025
Remaining : 15.03 Lacs
Demand : 2.00 Lacs
Allotment : 2.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 60.45 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 years 4 months ago
14 Jan 2013
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
कार्य पूर्ण। अधिकांश कास्तकारो का प्रतिकर का भुगतान कर दिया गया ह। शेष अनुपस्थित कास्तकारा को वितरित करने की कार्यवाही गतिमान।गया ह। शेष कास्तकारा को वितरित करने की कार्यवाही की जा रही है। -- as on 09-Feb-2024
Physical Peramenters