Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
125W8 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5706 (1)/।।।(2) /10-22 (प्रा0आ0)/2010, दि0 04 नवम्बर 2010
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 25.20 Lacs
Resanction Cost : 25.20 Lacs
Exp. Upto Last Fy : 9.78 Lacs
For CFY 2024-2025
Remaining : 15.42 Lacs
Demand : 5.00 Lacs
Allotment : 3.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.78 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
13 years 6 months ago
04 Nov 2010
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
कार्य पूर्ण। शेष मुआवजा भुगतान की कार्यवाही गतिमान। -- as on 29-Apr-2024
Physical Peramenters