Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 0 | 1 | 0 | 0 |
126W106 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादंश संख्या 802/एक्स॰एक्स॰-8/2018-4(9)2018 दिनांक 28.11.2018
TS Amount (lakhs) : 200 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
200.00
Resanction Cost :
200.00
Tentative Cost :
200.00
Exp. Upto Last Fy : 176.12
For CFY 2024-2025
Remaining : 23.88
Demand : 23.87
Allotment : 23.87
Exp in CFY : 15.57
Total Up to Date Exp : 191.70
Construction Started
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
5 years 7 months ago
28 Nov 2018
Tentative Completion date:
3 years 2 weeks ago
30 Jun 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 03-Jun-2024
Physical Peramenters