Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
126W12 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 572/111-2/06-08 (प्रा.आ.)/06 दिनांक 28/03/2006 एवं 574/।।।(2)/19-08(प्रा॰आ॰)/2006 दिनांक 04 फरवरी 2019
TS Amount (lakhs) : 110.88 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
33.60
Resanction Cost :
114.49
Tentative Cost :
114.49
Exp. Upto Last Fy : 111.98
For CFY 2024-2025
Remaining : 2.51
Demand : 0.51
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 111.98
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 3 months ago
28 Mar 2006
Tentative Completion date:
4 years 1 month ago
31 May 2020
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: Compensation Dispute
श॰सं॰ 390/10-4-17 /1(117)/2016 दि॰ 02.08.2017 द्वारा वन भूमि की विधिवत् स्वीकृति प्राप्त। 2.00 किमी॰ मे कार्य पूर्ण। मुआवजा भुगतान शेष। -- as on 01-Feb-2022
Physical Peramenters