Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
126W121 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 642/।।।(2)/19-6 (एम॰एल॰ए॰)/2017 टी॰सी॰।।। दिनांक 12 फरवरी 2020
TS Amount (lakhs) : 60 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.00
Resanction Cost :
60.00
Tentative Cost :
60.00
Exp. Upto Last Fy : 50.27
For CFY 2024-2025
Remaining : 9.73
Demand : 7.73
Allotment : 6.36
Exp in CFY : 5.89
Total Up to Date Exp : 56.16
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 5 months ago
12 Feb 2020
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-Jul-2024
Physical Peramenters