Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
126W155 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2304/III(2)/21-06(एम॰एल॰ए)/2017 TC
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
81.01
Resanction Cost :
81.01
Tentative Cost :
81.01
Exp. Upto Last Fy : 76.90
For CFY 2024-2025
Remaining : 4.11
Demand : 2.11
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 76.90
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
22 Jul 2021
Tentative Completion date:
1 year 6 months ago
30 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
03 किमी0 लं0 के सापेक्ष 3.00 किमी0 लं0 मे पहाड कटान का कार्य पूर्ण। दायित्व शेष। -- as on 02-May-2022
Physical Peramenters