Work Profile Report [126W157]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 327-(1)/।।।(2)/21-06(एम॰एल॰ए॰)/2017 T.C.I दि॰ 03.01.2022
TS Amount (lakhs) : 35.53 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.53
Resanction Cost :
35.53
Tentative Cost :
35.53
Exp. Upto Last Fy :
20.19
For CFY 2024-2025
Remaining :
15.34
Demand :
15.34
Allotment :
15.34
Exp in CFY :
14.56
Total Up to Date Exp :
34.75
Work completed
Sanction on : 2 years 10 months ago
03 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 10 months 3 weeks ago
30 Dec 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष। -- as on 03-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand