Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.400 | 0.1 | 0.100 | 0.000 |
126W157 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 327-(1)/।।।(2)/21-06(एम॰एल॰ए॰)/2017 T.C.I दि॰ 03.01.2022
TS Amount (lakhs) : 35.53 Lacs
Financial Detail
Sanction Cost : 35.53 Lacs
Resanction Cost : 35.53 Lacs
Exp. Upto Last Fy : 20.19 Lacs
For CFY 2024-2025
Remaining : 15.34 Lacs
Demand : 15.34 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 20.19 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
2 years 4 months ago
03 Jan 2022
Tentative Completion date:
4 months 2 weeks ago
30 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.5 किमी0 लं0 के सापेक्ष 1.40 किमी0 लं0 में पहाड कटान का कार्य पूर्ण।शेष कार्य प्रगति पर। -- as on 01-Jan-2024
Physical Peramenters