Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
126W158 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 327-(1)/।।।(2)/21-06(एम॰एल॰ए॰)/2017 T.C.I दि॰ 03.01.2022
TS Amount (lakhs) : 99.53 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
99.53
Resanction Cost :
99.53
Tentative Cost :
99.53
Exp. Upto Last Fy : 95.45
For CFY 2024-2025
Remaining : 4.08
Demand : 2.08
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 95.45
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
03 Jan 2022
Tentative Completion date:
1 year 3 months ago
25 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 01-May-2023
Physical Peramenters