Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 |
126W160 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 403/XXXVI(2)/22/18-budget/2020
TS Amount (lakhs) : 505.59 Lacs
Financial Detail
Sanction Cost : 484.84 Lacs
Resanction Cost : 505.59 Lacs
Exp. Upto Last Fy : 196.61 Lacs
For CFY 2024-2025
Remaining : 308.98 Lacs
Demand : 300.00 Lacs
Allotment : 5.22 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 196.61 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 36 %
Up to Date : 45 %
Sanction on :
1 year 11 months ago
09 Jun 2022
Tentative Completion date:
6 months 2 weeks from now
09 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
आर0सी0सी0 फ्रेम स्ट्रक्चर का कार्य पूर्ण। ईट चिनाई का कार्य प्रगति पर। -- as on 01-May-2024
Physical Peramenters