Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 |
126W160 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 403/XXXVI(2)/22/18-budget/2020
TS Amount (lakhs) : 505.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
484.84
Resanction Cost :
505.59
Tentative Cost :
505.59
Exp. Upto Last Fy : 196.61
For CFY 2024-2025
Remaining : 308.98
Demand : 300.00
Allotment : 5.22
Exp in CFY : 0.00
Total Up to Date Exp : 196.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 36 %
Up to Date : 60 %
Sanction on :
2 years 1 month ago
09 Jun 2022
Tentative Completion date:
4 months 3 weeks from now
09 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
आर0सी0सी0 फ्रेम स्ट्रक्चर का कार्य पूर्ण। ईट चिनाई एवं प्लास्टर का कार्य प्रगति पर। -- as on 02-Jul-2024
Physical Peramenters