Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 68 | 68 | 68 | 0 |
126W175 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के ई॰ फाईल सं॰ 49189 दि॰ 15.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 13.60 Lacs
Resanction Cost : 13.60 Lacs
Exp. Upto Last Fy : 10.86 Lacs
For CFY 2024-2025
Remaining : 2.74 Lacs
Demand : 2.74 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 10.86 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 2 months ago
15 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्थल चयन आख्या अधीक्षण अभियन्ता 7 वाॅ वृत्त लो0नि0वि0 गोपेश्वर द्वारा दि0 09.12.2023 को अनुमोदित। डिजायन एवं ड्राइंग का कार्य प्रगति पर। -- as on 01-Mar-2024
Physical Peramenters