Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
126W178 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : अपर सचिव, उत्तराखण्ड़ शासन के ई॰ फाईल सं॰ 49189 दि॰ 19.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
7.50
Resanction Cost :
7.50
Tentative Cost :
7.50
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 7.40
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 1 month ago
19 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
ग्राम वासियों द्वारा समरेखण विवाद किया जा रहा है। -- as on 30-Mar-2024
Physical Peramenters