Work Profile Report [126W189]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : सयुक्त सचिव उत्तराखण्ड शासन के ई॰फाईल सं॰- 49189 दि॰ 28.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
92.96
Resanction Cost :
92.96
Tentative Cost :
92.96
Exp. Upto Last Fy :
31.42
For CFY 2024-2025
Remaining :
61.54
Demand :
51.16
Allotment :
54.93
Exp in CFY :
54.93
Total Up to Date Exp :
86.35
Work completed
Sanction on : 1 year 4 months ago
28 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
83 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष। -- as on 28-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: