Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 2.500 | 0.5 | 0.500 | 0.000 |
126W189 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : सयुक्त सचिव उत्तराखण्ड शासन के ई॰फाईल सं॰- 49189 दि॰ 28.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 92.96 Lacs
Resanction Cost : 92.96 Lacs
Exp. Upto Last Fy : 31.42 Lacs
For CFY 2024-2025
Remaining : 61.54 Lacs
Demand : 45.00 Lacs
Allotment : 22.36 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 31.42 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 83 %
Up to Date : 83 %
Sanction on :
9 months 3 weeks ago
28 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 किमी0 लं0 के सापेक्ष 2.500 किमी0 लं0 में पहाड कटान का कार्य पूर्ण।शेष कार्य प्रगति पर। -- as on 14-Mar-2024
Physical Peramenters