Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 2.4 | 2.4 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 15 | 15 | 15 | 0 |
126W19 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 811/111 (2)/14-50 (प्रा.आ.)/2013 दिनांक 08/02/2014
TS Amount (lakhs) : 217.34 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
217.34
Resanction Cost :
217.34
Tentative Cost :
217.34
Exp. Upto Last Fy : 206.66
For CFY 2024-2025
Remaining : 10.68
Demand : 2.68
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 206.66
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 5 months ago
08 Feb 2014
Tentative Completion date:
3 years 8 months ago
31 Oct 2020
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 कि॰मी॰ के विरूद्व 2.40 कि॰मी॰ में पी॰सी॰ तक का कार्य पूर्ण। शेष 0.6 कि॰मी॰ में सोलिंग तक पूर्ण। fकमी0 3 में fस्थत 15 मी0 स्पान आर0सी0सी0 पुfलया का fनर्माण कार्य पूर्ण। दाfयत्व शेष। -- as on 30-Jul-2021
Physical Peramenters