Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 13.9 | 13.9 | 13.9 | 0 |
126W192 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन देहरादून के ई फाईल सं॰ 48456 दि॰ 10.08.2023
TS Amount (lakhs) : 195.16 Lacs
Financial Detail
Sanction Cost : 195.16 Lacs
Resanction Cost : 195.16 Lacs
Exp. Upto Last Fy : 97.58 Lacs
For CFY 2024-2025
Remaining : 97.58 Lacs
Demand : 97.58 Lacs
Allotment : 40.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 97.58 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 65 %
Sanction on :
9 months 1 week ago
10 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
7.50 किमी0 लम्बाई में पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters