Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
126W193 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4088/।।।(2)/2023-प्रा0आ0)/2023 दि॰ 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 590.83 Lacs
Resanction Cost : 590.83 Lacs
Exp. Upto Last Fy : 116.50 Lacs
For CFY 2024-2025
Remaining : 474.33 Lacs
Demand : 460.00 Lacs
Allotment : 200.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 116.50 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 28 %
Up to Date : 45 %
Sanction on :
6 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.15 किमी0 लम्बाई मंे क्र्रैश बैरियर लगाने का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters