Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 40.25 | 40.25 | 0.000 | 40.25 | 0.000 | 0.000 |
126W195 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के पत्र संख्या 5347/।।।(2)/2023-01(प्रा0आ0)/2023 दि0 05.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
92.88
Resanction Cost :
92.88
Tentative Cost :
92.88
Exp. Upto Last Fy : 0.06
For CFY 2024-2025
Remaining : 92.82
Demand : 60.00
Allotment : 52.00
Exp in CFY : 51.94
Total Up to Date Exp : 52.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 80 %
Sanction on :
7 months 1 week ago
05 Dec 2023
Tentative Completion date:
4 weeks 1 day from now
16 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रैश बैरियर लगाने का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 02-Jul-2024