Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
126W196 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के शासनादेश संख्या- 272/।।।(2)/2024-01 (प्रा0आ0)/2023 दि0 31.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 275.80 Lacs
Resanction Cost : 275.80 Lacs
Exp. Upto Last Fy : 91.96 Lacs
For CFY 2024-2025
Remaining : 183.84 Lacs
Demand : 183.84 Lacs
Allotment : 125.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 91.96 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 66 %
Sanction on :
3 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.88 किमी0 लम्बाई मंे क्र्रैश बैरियर लगाने का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters