Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 15 | 15 | 15 | 0 |
126W198 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के ई॰फाईल संख्या 67047/06 दि॰ 06.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.15
Resanction Cost :
3.15
Tentative Cost :
3.15
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 3.05
Demand : 3.05
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 months 1 week ago
06 Feb 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इस कार्यालय पत्रांक 263/निविदा (2ए0सी0) दिनांक 24.02.2024 द्वारा निविदा आमंत्रित कर दिनांक 04.03.2024 को खोली गयी, जिसमें कोई भी निविदा प्राप्त नहीं हुयी। पुनः इस कार्यालय पत्रांक 665/निविदा (2ए0सी0) दिनांक 07.06.2024 द्वारा निविदा आमंत्रित जो कि दिनांक 18.07.2024 को खोली जानी है। -- as on 02-Jul-2024
Physical Peramenters