Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
126W5 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4305 (1)/111 (2)/11-16 (मु.मं.घो.)/2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy : 18.51
For CFY 2024-2025
Remaining : 6.69
Demand : 6.69
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.51
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
12 years 10 months ago
16 Sep 2011
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: Compensation Dispute
प्रथम चरण का कार्य पूर्ण। मुआवजा भुगतान की कार्यवाही की जा रही है। शा0संख्या 387 / 10 - 4 - 17 / 1(152) /2016 दिनांक 16 अगस्त 2017 द्वारा विधिवत् स्वीकृति प्राप्त। उक्त कार्य की द्वितीय चरण की स्वीकृति शा0संख्या 1623 / ।।।(2) / ं17-06 (एम0एल0ए0) /2017 टी0सी0 दिनांक 03.08.2017 द्वारा लागत रू0 102.68 लाख की प्राप्त। -- as on 31-Mar-2021
Physical Peramenters