Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
126W6 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 5377/111 (2)/13-13 (मु.मं.घो.)/2012 दिनांक 14/01/2013
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 25.20 Lacs
Resanction Cost : 25.20 Lacs
Exp. Upto Last Fy : 6.06 Lacs
For CFY 2024-2025
Remaining : 19.14 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.06 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 years 4 months ago
14 Jan 2013
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: Compensation Dispute
इस कार्यालय पत्रांक 486/1 एल0ए0 दि0 27.04.2024 द्वारा आपत्त्यिों का निराकरण प्रभागीय वनाधिकारी वन्यजीव प्रभाग गोपेश्वर को प्रेषित। -- as on 02-May-2024
Physical Peramenters