Work Profile Report [127W12]
Fin Plan
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या - 1444/VI(1)/2020-03(17)/2020 dated 2020-09-24
TS Amount (lakhs) : 595.24 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
595.24
Resanction Cost :
607.47
Tentative Cost :
607.47
Exp. Upto Last Fy :
281.12
For CFY 2024-2025
Remaining :
326.35
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
281.12
none
Sanction on : 4 years 2 months ago
24 Sep 2020
Physical Progress:
At start of FY 2024-2025 :
6 %
Up to Date :
6 %
Tentative Completion date on : 1 year 11 months ago
04 Dec 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work will be started after all near building plinth level has been Completed. -- as on 01-May-2023
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Saraswati Bailley Bridge. VVIP Helipad Bailley Bridge.