Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.92 | 1.92 | 1.920 | 0 | 0.000 | 0.000 |
128W125 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2661/।।।(2)/17-04(एम0एल0ए0)/2017 दिं0 12.10.2017
TS Amount (lakhs) : 105.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
105.29
Resanction Cost :
105.29
Tentative Cost :
105.29
Exp. Upto Last Fy : 63.22
For CFY 2024-2025
Remaining : 42.07
Demand : 38.94
Allotment : 18.94
Exp in CFY : 18.94
Total Up to Date Exp : 82.16
Work completed
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 90 %
Sanction on :
6 years 9 months ago
12 Oct 2017
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 02-Jul-2024