Work Profile Report [128W126]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2661/।।।(2)/17-04(एम0एल0ए0)/2017 दिं0 12.10.2017
TS Amount (lakhs) : 151.54 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
151.54
Resanction Cost :
151.54
Tentative Cost :
151.54
Exp. Upto Last Fy :
137.40
For CFY 2025-2026
Remaining :
14.14
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
137.40
Construction Started
Sanction on : 7 years 5 months ago
12 Oct 2017
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
80 %
Tentative Completion date on : 11 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वन भूमि की विधिवत स्वीकृति प्राप्त। कार्य प्रगति में। -- as on 04-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: