Work Profile Report [128W126]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2661/।।।(2)/17-04(एम0एल0ए0)/2017 दिं0 12.10.2017
TS Amount (lakhs) : 151.54 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
151.54
Resanction Cost :
151.54
Tentative Cost :
151.54
Exp. Upto Last Fy :
137.40
For CFY 2025-2026
Remaining :
14.14
Demand :
10.00
Allotment :
10.00
Exp in CFY :
8.21
Total Up to Date Exp :
145.60
Construction Started
Sanction on : 7 years 8 months ago
12 Oct 2017
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
100 %
Tentative Completion date on : 3 days 5 hours from now
01 Jul 2025
Actual Completion Date : 2 months 1 week ago
20 Apr 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 18-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: