Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 2.500 | 0.5 | 0.500 | 0.000 |
128W127 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3976ए/।।।(2)/17-04(एम0एल0ए0)/ 2017टी0सी0 दिं0 12.12.2017
TS Amount (lakhs) : 145.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
142.50
Resanction Cost :
142.50
Tentative Cost :
142.50
Exp. Upto Last Fy : 118.95
For CFY 2024-2025
Remaining : 23.55
Demand : 17.22
Allotment : 11.23
Exp in CFY : 11.22
Total Up to Date Exp : 130.18
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
6 years 7 months ago
12 Dec 2017
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 02-Jul-2024
Physical Peramenters