Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.3 | 4.3 | 4.000 | 0.3 | 0.000 | 0.000 |
128W207 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 4819/।।।(2)/21-04(MLA)/2017 TC दिनांक 11.10.2021
TS Amount (lakhs) : 307.11 Lacs
Financial Detail
Sanction Cost : 307.11 Lacs
Resanction Cost : 307.11 Lacs
Exp. Upto Last Fy : 307.11 Lacs
For CFY 2024-2025
Remaining : 0.00 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 307.11 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
11 Oct 2021
Tentative Completion date:
4 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अनुरक्षण मद के अन्तर्गत कार्य किया जाना है। -- as on 16-Apr-2024
Physical Peramenters