Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 25.735 | 25.735 | 0.200 | 25.535 | 20.400 | 0.000 |
128W208 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: R.C.C Bridle Bridge Over Patal Gadhera near Bingad R.C.C Bridle Bridge Over Kot Gadhera near Satbhaiya Kot village
Administrative Approval Detail : शा0सं0 1178(।)/।।।(3)/2021-30(सी0आर0आई0एफ0)/2021 दिनांक 27.10.2021
TS Amount (lakhs) : 2337.06 Lacs
Financial Detail
Sanction Cost : 2,337.06 Lacs
Resanction Cost : 2,337.06 Lacs
Exp. Upto Last Fy : 426.77 Lacs
For CFY 2024-2025
Remaining : 1,910.29 Lacs
Demand : 1,400.00 Lacs
Allotment : 200.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 426.77 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
2 years 6 months ago
27 Oct 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डिफेक्ट कटिंग,मक डिस्पोजल, स्कपर निर्माण, दीवार निर्माण कार्य एवं बी0एम0/एस0डी0बी0सी0 का कार्य प्रगति में। -- as on 02-May-2024
Physical Peramenters