Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 5 | 5 | 0 | 5 | 0 | 0 |
Span of Bridges [m] | 102.32 | 102.32 | 0.000 | 102.32 | 0.000 | 0.000 |
128W223 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण विभाग अनुभाग-2 की ई फाईल सं0 32100 दिनांक 02.03.2023
TS Amount (lakhs) : 30.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.70
Resanction Cost :
30.70
Tentative Cost :
30.70
Exp. Upto Last Fy : 17.44
For CFY 2024-2025
Remaining : 13.26
Demand : 13.00
Allotment : 2.00
Exp in CFY : 0.00
Total Up to Date Exp : 17.44
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
1 year 4 months ago
02 Mar 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सेतुओं का स्थल चयन,जियो टेक्निकल एवं ड्राफ्ट डिजाइन डी0पी0आर0 का कार्य पूर्ण। सेतुओं के डिजाइन का कार्य गतिमान। दिनांक 19.06.2024 को संयुक्त निरीक्षण पूर्ण। आख्या अपेक्षित। -- as on 02-Jul-2024
Physical Peramenters