Work Profile Report [128W250]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश संख्या 4088/।।।(2)/2023-(प्रा0आ0)/2023 दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.58
Resanction Cost :
81.58
Tentative Cost :
81.58
Exp. Upto Last Fy :
45.47
For CFY 2024-2025
Remaining :
36.11
Demand :
36.11
Allotment :
35.00
Exp in CFY :
12.07
Total Up to Date Exp :
57.53
Construction Started
Sanction on : 1 year 3 weeks ago
01 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
60 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में। -- as on 02-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand