Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.2 | 9.2 | 0.000 | 9.2 | 0.000 | 0.000 |
128W251 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4088/।।।(2)/2023-(प्रा0आ0)/2023 दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 22.89 Lacs
Resanction Cost : 22.89 Lacs
Exp. Upto Last Fy : 14.36 Lacs
For CFY 2024-2025
Remaining : 8.53 Lacs
Demand : 8.53 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 14.36 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 70 %
Sanction on :
6 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 02-Mar-2024
Physical Peramenters