Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 1.500 | 0.000 |
128W253 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण विभाग अनुभाग-2 की ई फाईल सं0 49531/04 दिनांक 01.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 232.38 Lacs
Resanction Cost : 232.38 Lacs
Exp. Upto Last Fy : 26.93 Lacs
For CFY 2024-2025
Remaining : 205.45 Lacs
Demand : 180.00 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 26.93 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
3 months 2 weeks ago
01 Feb 2024
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 30-Mar-2024
Physical Peramenters