Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 0.000 | 12 | 0.000 | 0.000 |
128W257 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण विभाग अनुभाग-2 की ई फाईल सं0 49531/04 दिनांक 14.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.00
Resanction Cost :
18.00
Tentative Cost :
18.00
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 17.90
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 3 days ago
14 Mar 2024
Tentative Completion date:
1 year 8 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण की कार्यवाही की जा रही है। -- as on 15-Mar-2024
Physical Peramenters