Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.21 | 2.21 | 1.110 | 1.1 | 0.000 | 0.000 |
129W532 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 931/।।।(2)/20-33(एम.एल.ए.)2017टीसीआई दिनांक 30.03.2021
TS Amount (lakhs) : 88.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.76
Resanction Cost :
95.42
Tentative Cost :
95.42
Exp. Upto Last Fy : 52.43
For CFY 2024-2025
Remaining : 42.99
Demand : 0.33
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 52.43
Work completed
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 100 %
Sanction on :
3 years 3 months ago
30 Mar 2021
Tentative Completion date:
4 months 2 days ago
15 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। 04/2024 दायित्व शेष। उक्त कार्य 5 वर्षिय अनुरक्षण के अन्तर्गत है। -- as on 10-May-2024
Physical Peramenters