Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.1 | 1.1 | 1.100 | 0 | 0.000 | 0.000 |
129W534 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 931/।।।(2)/20-33(एम.एल.ए.)2017टीसीआई दिनांक 30.03.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 60.98 Lacs
Resanction Cost : 65.55 Lacs
Exp. Upto Last Fy : 55.55 Lacs
For CFY 2024-2025
Remaining : 10.00 Lacs
Demand : 0.30 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 55.55 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
30 Mar 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
1 year 1 month ago
31 Mar 2023
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 25-Apr-2023
Physical Peramenters