Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.175 | 1.175 | 1.170 | 0.0050000000000001 | 0.000 | 0.000 |
129W544 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Govt. Order No. 1420/(1)/III(2)/21-34(MLA)/2017 Dt. 25.05.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
117.03
Resanction Cost :
117.03
Tentative Cost :
117.03
Exp. Upto Last Fy : 36.15
For CFY 2024-2025
Remaining : 80.88
Demand : 80.88
Allotment : 79.40
Exp in CFY : 79.40
Total Up to Date Exp : 115.56
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
25 May 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
3 months 2 weeks ago
31 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व अवशेष -- as on 30-Apr-2024
Physical Peramenters