Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.26 | 4.26 | 4.260 | 0 | 0.000 | 0.000 |
129W624 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Govt. Order No. 5457(1)/III(2)/21-34(MLA)/2017 T.C-II Dt. 16.11.2021
TS Amount (lakhs) : 157.17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
157.17
Resanction Cost :
159.98
Tentative Cost :
159.98
Exp. Upto Last Fy : 138.02
For CFY 2024-2025
Remaining : 21.96
Demand : 0.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 138.02
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
16 Nov 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 19-Dec-2023
Physical Peramenters