Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.44 | 1.44 | 0.800 | 0.64 | 0.640 | 0.000 |
129W651 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-47899, लोक निर्माण अनुभाग-2 दिनांक 13.03.2023
TS Amount (lakhs) : 79.33 Lacs
Financial Detail
Sanction Cost : 79.33 Lacs
Resanction Cost : 83.98 Lacs
Exp. Upto Last Fy : 63.17 Lacs
For CFY 2024-2025
Remaining : 20.81 Lacs
Demand : 16.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 63.17 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
1 year 2 months ago
13 Mar 2023
Tentative Completion date:
2 months 4 days ago
15 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
PC का कार्य प्रगति पर। -- as on 06-Mar-2024
Physical Peramenters