Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.44 | 1.44 | 0.800 | 0.64 | 0.640 | 0.000 |
129W651 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-47899, लोक निर्माण अनुभाग-2 दिनांक 13.03.2023
TS Amount (lakhs) : 79.33 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
79.33
Resanction Cost :
83.98
Tentative Cost :
83.98
Exp. Upto Last Fy : 63.17
For CFY 2024-2025
Remaining : 20.81
Demand : 16.00
Allotment : 16.00
Exp in CFY : 15.21
Total Up to Date Exp : 78.37
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
13 Mar 2023
Tentative Completion date:
4 months 2 days ago
15 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
work completed -- as on 19-May-2024
Physical Peramenters