Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.600 | 0 | 0.000 | 0.000 |
129W652 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-49684, लोक निर्माण अनुभाग-2 दिनांक 28.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.72
Resanction Cost :
41.72
Tentative Cost :
41.72
Exp. Upto Last Fy : 11.04
For CFY 2024-2025
Remaining : 30.68
Demand : 20.00
Allotment : 12.86
Exp in CFY : 12.86
Total Up to Date Exp : 23.90
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
1 month 1 week ago
05 Jun 2024
Actual Completion Date:
2 months 1 week ago
06 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 27-Mar-2024
Physical Peramenters