Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.55 | 0.55 | 0.550 | 0 | 0.000 | 0.000 |
129W655 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-51297, लोक निर्माण अनुभाग-2 दिनांक 28.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.54
Resanction Cost :
37.54
Tentative Cost :
37.54
Exp. Upto Last Fy : 21.59
For CFY 2024-2025
Remaining : 15.95
Demand : 8.00
Allotment : 5.00
Exp in CFY : 4.93
Total Up to Date Exp : 26.52
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 18-Jan-2024
Physical Peramenters