Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
129W661 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-51297, लोक निर्माण अनुभाग-2 दिनांक 28.03.2023
TS Amount (lakhs) : 67.07 Lacs
Financial Detail
Sanction Cost : 67.07 Lacs
Resanction Cost : 72.10 Lacs
Exp. Upto Last Fy : 62.09 Lacs
For CFY 2024-2025
Remaining : 10.01 Lacs
Demand : 0.39 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 62.09 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
28 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। 11/2023 दायित्व शेष। -- as on 12-Jan-2024