Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.61 | 0.61 | 0.610 | 0 | 0.000 | 0.000 |
129W665 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-49430, लोक निर्माण अनुभाग-2 दिनांक 25.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.91
Resanction Cost :
26.91
Tentative Cost :
26.91
Exp. Upto Last Fy : 19.41
For CFY 2024-2025
Remaining : 7.50
Demand : 7.50
Allotment : 4.95
Exp in CFY : 4.95
Total Up to Date Exp : 24.36
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
25 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 30-Apr-2024