Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.300 | 0.2 | 0.200 | 0.000 |
129W671 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-48594, दिनांक 19.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
46.54
Resanction Cost :
46.54
Tentative Cost :
46.54
Exp. Upto Last Fy : 18.04
For CFY 2024-2025
Remaining : 28.50
Demand : 19.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.04
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 60 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
ग्रामीणों का जल निकासी का विवाद होने के कारण कार्य बाधित। -- as on 30-Jun-2024
Physical Peramenters