Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.83 | 0.83 | 0.830 | 0 | 0.000 | 0.000 |
129W674 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-48594, दिनांक 19.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
56.48
Resanction Cost :
56.48
Tentative Cost :
56.48
Exp. Upto Last Fy : 19.33
For CFY 2024-2025
Remaining : 37.15
Demand : 30.00
Allotment : 16.04
Exp in CFY : 16.04
Total Up to Date Exp : 35.37
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
4 months 1 week ago
06 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व अवशेष -- as on 30-Apr-2024
Physical Peramenters